County Supervisors approve RCS lease for Red Mountain lookout station / Black Mountain New Tower and Building

Come here to talk about the San Diego and Imperial County Regional Communications System. This is a great resource to share talkgroups and information about the countywide RCS.
Post Reply
Brian
Posts: 1454
Joined: Thu Oct 21, 2004 8:54 pm

County Supervisors approve RCS lease for Red Mountain lookout station / Black Mountain New Tower and Building

Post by Brian »

County Supervisors approve RCS lease for Red Mountain lookout station

San Diego County will be leasing a portion of the California Department of Forestry and Fire Protection telecommunications site at Cal Fire’s Red Mountain lookout station.

A 5-0 San Diego County Board of Supervisors vote, Aug. 4, authorized the director of the county’s Department of General Services to execute the lease agreement, authorized the Department of General Services director to amend the lease as needed for future equipment configuration modifications and found the lease categorically exempt from California Environmental Quality Act review. The initial lease will be for 10 years retroactive to July 1, and three lease options if exercised would extend the lease to Dec. 31, 2041.

https://www.villagenews.com/story/2020/ ... 63040.html


August 4th Agenda
https://www.sandiegocounty.gov/content/ ... UPERVISORS


Attachments/Supporting Documentation
Board Letter:
DGS 08.04.20 Sheriff RCS Lease at Red Mt
https://bosagenda.sandiegocounty.gov/co ... 7e80beb757

Attachments:
Approval Log
https://bosagenda.sandiegocounty.gov/co ... 7e80beb756

Minute Orders:
04AUG2020_Reg_mo_14
https://bosagenda.sandiegocounty.gov/co ... 7e80bf162e
Brian
Posts: 1454
Joined: Thu Oct 21, 2004 8:54 pm

Lake Morena - NextGen RCS Radio Site and Facility Project

Post by Brian »

Another RCS site project

Lake Morena - Project - March, 2020
Construct a new NextGen RCS Radio Site and Facility.
The estimated cost of the construction is $418,100.
https://www.sandiegocounty.gov/content/ ... 020sop.pdf
Brian
Posts: 1454
Joined: Thu Oct 21, 2004 8:54 pm

Black Mountain new County Radio Tower and building

Post by Brian »

Black Mountain stuff moving out of City building/tower, to new county radio tower and county building.
(Note: Black Mountain location is part of the RCS Nextgen West Cell.)

--------------------------------------

SHERIFF - AUTHORIZATION TO EXERCISE A CONTRACT OPTION TO MOTOROLA SOLUTIONS CONTRACT FOR THE REGIONAL COMMUNICATIONS SYSTEM DEVELOPMENT OF THE BLACK MOUNTAIN SITE AND FACILITY

Board Meeting: BOARD OF SUPERVISORS, 11/17/2020 (Agenda Item #4)
https://www.sandiegocounty.gov/content/ ... UPERVISORS

Board Letter:
SHF BL AUTHORIZATION TO EXERCISE A CONTRACT FOR BLACK MOUNTAIN FINAL
https://bosagenda.sandiegocounty.gov/co ... 7e80c3d614 Attachments:
BM Approval Log
https://bosagenda.sandiegocounty.gov/co ... 7e80c3d615

The RCS provides the County and numerous public safety agencies with day-to-day public safety
and emergency responder communications. To support radio communications in the western
region of the county, the Sheriff's Department operates an existing RCS site, on a tower owned by
the City of San Diego, at Black Mountain. The County lease with the City of San Diego for space
on their tower is expired and on hold-over. The City of San Diego's tower is structurally overloaded
with radio equipment and has been identified as in need of replacement.
In order to provide
continued communications connectivity to existing RCS sites, the Sheriff's Department plans to
construct a new tower on a County leased radio communications facility. A County managed tower
and facility will ensure the long-term operational viability and security of the RCS. The Sheriff
paid $24,997 in Fiscal Year 2019-20 for space on the City of San Diego's tower.

This is a request to authorize the Director of the Department of Purchasing and Contracting to
exercise a Phase Three contract option for the RCS Replacement Contract with Motorola Solutions
Inc. for the new Black Mountain communications radio tower.

The proposed project would result in the replacement of an existing concrete foundation,
construction of a new antenna support structure, relocation of existing antenna equipment from the
existing facility to the new structure, and installation of connection cables. No additional support
equipment is required, as an emergency generator and equipment shelter exist and would continue
to be utilized.

------------------------------------------------------
PREVIOUS RELEVANT BOARD ACTIONS:
March 24, 2020 (1), Authorization to exercise a contract option to Motorola Solutions contract for the Regional Communications System Development of the Lake Morena Site and Facility;

December 10, 2019 (3), Authorization to exercise a contract option to Motorola Solutions contract for the Regional Communications System Development of the San Ysidro Site and Facility;

June 19, 2018 (3), Authorization to exercise a contract option to Motorola Solutions contract for the Regional Communications System Development of the Pala Site and Facility;

September 12, 2017 (2) Authorization to exercise a contract option to Motorola Solutions
contract for the Regional Communications System Replacement for San Onofre Peak, Marine Corps Base Camp Pendleton;

June 27, 2017 (1) Authorization to exercise a contract option to Motorola Solutions contract for the Regional Communications System Replacement;

November 15, 2016 (4), Authorization to exercise a contract option to Motorola Solutions contract for the Regional Communications System Replacement;

June 9, 2015 (1), Authorization to issue a request for proposal and award a phased contract for the upgrade of the Regional Communications System; December 3, 2013 (6), Approval of the agreement between and among the County of San Diego and participating cities and jurisdictions regarding the Next Generation Regional Communications System.

--------------------------------------------------------